Liyel Imoke, a former governor of Cross River, has told the Federal Capital Territory (FCT) high court in Apo that the federal executive council (FEC) did not approve the $6 billion Mambilla power project contract awarded to Sunrise Power Transmission Company Limited.
Imoke, who testified as the sixth prosecution witness in the
trial of Olu Agunloye, former minister of power, said the contract award was
invalid because it was not approved by the council.
According to a statement by the Economic and Financial
Crimes Commission (EFCC), Imoke gave the testimony on Monday while being
cross-examined by Adeola Adedipe, counsel to Agunloye.
Agunloye is facing an amended seven-count charge bordering
on official corruption and the alleged fraudulent award of the Mambilla power
project contract to Sunrise Power while he was minister of power and steel
between 2002 and 2003.
At an earlier sitting on October 19, Imoke told the court
that FEC never approved the contract. He said he reached that conclusion after
reading the minutes of the May 21, 2003 meeting, where the project was
deliberated.
However, during cross-examination on November 2, Adedipe
questioned whether the minutes were subsequently adopted by the succeeding
council, noting that the May 21 meeting was the last FEC meeting before the
cabinet was dissolved.
Imoke had said he was not privy to the adoption of the
minutes because he was not a member of
council at the time.
During Monday’s proceedings, Imoke clarified that he was
sworn in on July 15, 2003, and not August, as earlier stated. He said he
attended the FEC meeting in July 2003, where the minutes of the May 21, 2003
meeting were adopted.
“My Lord, as I mentioned at the beginning of today’s
proceedings, I was sworn in on 15th July, 2003, not August as earlier
mentioned. When I checked my records, I saw that I participated in the FEC
meeting of July, 2003, where the minutes of the 16th FEC meeting of May 21,
2003 was adopted,” he said.
He added that the proceedings of the July meeting were not
included in the exhibit file before the court.
Explaining the difference between extracts of FEC meetings
and the full council conclusions, Imoke said extracts are usually forwarded to
the relevant ministries, while the full conclusions are kept or distributed to
offices under the office of the secretary to the government of the federation.
When shown exhibits EFCC 3K and EFCC 3D, comprising letters
from the ministry of power forwarding the FEC conclusions and extracts,
respectively, Imoke said both documents were the same in substance and form.
The witness was also asked whether, during his tenure as
minister, he had proposed awarding contracts on a build-operate-transfer basis
or through outright purchase. He said he could not recall.
At the end of the cross-examination, Abba Mohammed,
prosecution counsel, sought an adjournment to address fresh issues raised
during the proceedings.
Jude Onwuegbuzie, the presiding judge, adjourned the case
until November 19 for re-examination.
In September, Nigeria won a separate arbitration case
against Sunrise Power over the Mambilla project, with the International Chamber
of Commerce (ICC) tribunal in Paris dismissing the company’s $2.35 billion
claim against the country.
The tribunal also ordered Sunrise and its promoter, Leno
Adesanya, to reimburse Nigeria 75 percent of its legal fees and expenses
incurred during the arbitration.
Advertise on NigerianEye.com to reach thousands of our daily users

No comments
Post a Comment
Kindly drop a comment below.
(Comments are moderated. Clean comments will be approved immediately)
Advert Enquires - Reach out to us at NigerianEye@gmail.com